Location: National Energy Technology Lab, Pittsburgh, PA
Client: Department of Energy
Award Date: March 2021
Completion Date: May 2024
Original Contract: $15,884,395

GbOSS is the prime contractor for this 8,000 SF Tier III, 1.2 MW enterprise Data Center. The project provides for 3,500 SF renovations in Building 83 for office space/visualization gallery and related telecommunication space, and a two-story addition with 2,200 SF data hall at ground level, approximate 1,800 SF electrical space, telecommunication room and access corridors.